Tappaghan is operational in Fermanagh and Omagh with a recorded capacity of 19.5 MW, and has been generating since 2005-02-01.

19.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2005-02-01
Wind Onshore
Technology
Greencoat UK Wind
Fermanagh and Omagh
Authority
Northern Ireland

Planning and build timeline

Application submitted2002-08-01
Permission granted2003-11-03
15 months after submission
Operational2005-02-01
15 months after consent

Fermanagh and Omagh’s record on onshore wind

Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh

Other built sites within 15 km

SiteMWDistance
Tappaghan Extension
Wind Onshore · Operational
90 km
Crighshane
Wind Onshore · Operational
32.211 km
Thornog Windfarm Extension
Wind Onshore · Operational
9.211 km
Thornog Windfarm
Wind Onshore · Operational
9.211 km
Lough Hill
Wind Onshore · Operational
10.511.3 km
Castlecraig
Wind Onshore · Operational
2511.7 km
Church Hill
Wind Onshore · Operational
18.411.9 km
Bin Mountain
Wind Onshore · Operational
912 km

How big is Tappaghan?

Tappaghan has a recorded installed capacity of 19.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tappaghan?

REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tappaghan approved and built?

The application was submitted on 2002-08-01. Permission was granted on 2003-11-03, 15 months later. The site became operational on 2005-02-01, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3130.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council