Renewable sitesChurch Hill

Church Hill

Church Hill is operational in Derry City and Strabane with a recorded capacity of 18.4 MW, and has been generating since 2012-06-01.

18.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-06-01
Wind Onshore
Technology
Greencoat (formerly Energia Renewables)
Derry City and Strabane
Authority
Northern Ireland

Planning and build timeline

Application submitted2005-04-06
Permission granted2007-04-26
25 months after submission
Operational2012-06-01
61 months after consent

Derry City and Strabane’s record on onshore wind

Derry City and Strabane has decided 42 onshore wind schemes and approved 79%, taking a median of 29.1 months. See every onshore wind scheme decision in Derry City and Strabane

Other built sites within 15 km

SiteMWDistance
Crighshane
Wind Onshore · Operational
32.23 km
Bin Mountain
Wind Onshore · Operational
97.1 km
Lough Hill
Wind Onshore · Operational
10.57.3 km
Castlecraig
Wind Onshore · Operational
258.5 km
Slieveglass
Wind Onshore · Operational
6.99.5 km
Tievenameenta
Wind Onshore · Operational
34.59.7 km
Thornog Windfarm Extension
Wind Onshore · Operational
9.211.2 km
Thornog Windfarm
Wind Onshore · Operational
9.211.2 km

How big is Church Hill?

Church Hill has a recorded installed capacity of 18.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Church Hill?

REPD records the operator as Greencoat (formerly Energia Renewables). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Church Hill approved and built?

The application was submitted on 2005-04-06. Permission was granted on 2007-04-26, 25 months later. The site became operational on 2012-06-01, 61 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4047.