Renewable sites › Tangy Wind Farm Extension/Tangy 2
Tangy Wind Farm Extension/Tangy 2
Tangy Wind Farm Extension/Tangy 2 is an operational 6 MW onshore wind farm in Argyll and Bute, generating since 17 June 2011. Planning permission was granted on 1 September 2005, 14 months after submission. Operator of record: Scottish and Southern Energy (SSE).
Planning and build timeline
| Application submitted | 1 July 2004 |
| Permission granted | 1 September 2005 14 months after submission |
| Operational | 17 June 2011 69 months after consent |
Screening a site of your own?
Argyll and Bute approves 58% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Tangy Wind Farm Extension/Tangy 2’s recorded coordinate — swap in your own postcode or coordinates.
Argyll and Bute’s record on onshore wind
Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 12.8 | 8.8 km |
Wind Onshore · Under Construction | 49.9 | 9.1 km |
Wind Onshore · Operational | 6.9 | 11 km |
Wind Onshore · Operational | 29.7 | 11.1 km |
Wind Onshore · Operational | 43.7 | 11.1 km |
Wind Onshore · Operational | 15 | 11.5 km |
Wind Onshore · Operational | 35 | 12.3 km |
How big is Tangy Wind Farm Extension/Tangy 2?
Tangy Wind Farm Extension/Tangy 2 has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tangy Wind Farm Extension/Tangy 2?
REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tangy Wind Farm Extension/Tangy 2 approved and built?
The application was submitted on 1 July 2004. Permission was granted on 1 September 2005, 14 months later. The site became operational on 17 June 2011, 69 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4024.