Renewable sites › Beinn an Tuirc Phase 2
Beinn an Tuirc Phase 2
Beinn an Tuirc Phase 2 is operational in Argyll and Bute with a recorded capacity of 43.7 MW, and has been generating since 2014-09-01.
Planning and build timeline
| Application submitted | 2005-07-07 |
| Permission granted | 2007-07-13 24 months after submission |
| Operational | 2014-09-01 86 months after consent |
Argyll and Bute’s record on onshore wind
Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Beinn an Tuirc Wind Onshore · Operational | 29.7 | 0 km |
Cnoc Donn Arnicle Wind Onshore · Operational | 15 | 1.4 km |
Beinn an Tuirc Windfarm Phase 3 Wind Onshore · Under Construction | 49.9 | 3.4 km |
Blary Hill Wind Farm Wind Onshore · Operational | 35 | 3.6 km |
Auchadaduie Wind Farm Wind Onshore · Operational | 6.9 | 5.6 km |
Deucheran Hill Wind Onshore · Operational | 15.8 | 6.8 km |
Tangy Wind Farm/Tangy 1 Wind Onshore · Operational | 12.8 | 10 km |
Tangy Wind Farm Extension/Tangy 2 Wind Onshore · Operational | 6 | 11.1 km |
How big is Beinn an Tuirc Phase 2?
Beinn an Tuirc Phase 2 has a recorded installed capacity of 43.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Beinn an Tuirc Phase 2?
REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Beinn an Tuirc Phase 2 approved and built?
The application was submitted on 2005-07-07. Permission was granted on 2007-07-13, 24 months later. The site became operational on 2014-09-01, 86 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4525.