Beinn an Tuirc Phase 2

Beinn an Tuirc Phase 2 is operational in Argyll and Bute with a recorded capacity of 43.7 MW, and has been generating since 2014-09-01.

43.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-09-01
Wind Onshore
Technology
Scottish Power Renewables
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted2005-07-07
Permission granted2007-07-13
24 months after submission
Operational2014-09-01
86 months after consent

Argyll and Bute’s record on onshore wind

Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute

Other built sites within 15 km

SiteMWDistance
Beinn an Tuirc
Wind Onshore · Operational
29.70 km
Cnoc Donn Arnicle
Wind Onshore · Operational
151.4 km
Beinn an Tuirc Windfarm Phase 3
Wind Onshore · Under Construction
49.93.4 km
Blary Hill Wind Farm
Wind Onshore · Operational
353.6 km
Auchadaduie Wind Farm
Wind Onshore · Operational
6.95.6 km
Deucheran Hill
Wind Onshore · Operational
15.86.8 km
Tangy Wind Farm/Tangy 1
Wind Onshore · Operational
12.810 km
Tangy Wind Farm Extension/Tangy 2
Wind Onshore · Operational
611.1 km

How big is Beinn an Tuirc Phase 2?

Beinn an Tuirc Phase 2 has a recorded installed capacity of 43.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Beinn an Tuirc Phase 2?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Beinn an Tuirc Phase 2 approved and built?

The application was submitted on 2005-07-07. Permission was granted on 2007-07-13, 24 months later. The site became operational on 2014-09-01, 86 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4525.