Beinn an Tuirc Phase 2

Beinn an Tuirc Phase 2 is an operational 43.7 MW onshore wind farm in Argyll and Bute, generating since 1 September 2014. Planning permission was granted on 13 July 2007, 24 months after submission. Operator of record: Scottish Power Renewables.

43.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2014
Wind Onshore
Technology
Scottish Power Renewables
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted7 July 2005
Permission granted13 July 2007
24 months after submission
Operational1 September 2014
86 months after consent

Screening a site of your own?

RedlineUK · £39

Argyll and Bute approves 58% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Beinn an Tuirc Phase 2’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Argyll and Bute’s record on onshore wind

Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
29.70 km
Wind Onshore · Operational
151.4 km
Wind Onshore · Under Construction
49.93.4 km
Wind Onshore · Operational
353.6 km
Wind Onshore · Operational
6.95.6 km
Wind Onshore · Operational
15.86.8 km
Wind Onshore · Operational
12.810 km
Wind Onshore · Operational
611.1 km

How big is Beinn an Tuirc Phase 2?

Beinn an Tuirc Phase 2 has a recorded installed capacity of 43.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Beinn an Tuirc Phase 2?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Beinn an Tuirc Phase 2 approved and built?

The application was submitted on 7 July 2005. Permission was granted on 13 July 2007, 24 months later. The site became operational on 1 September 2014, 86 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4525.