Novarly ParcelRenewable sites

Renewable sitesCnoc Donn Arnicle

Cnoc Donn Arnicle

Cnoc Donn Arnicle is operational in Argyll and Bute with a recorded capacity of 15 MW, and has been generating since 2001-10-01.

15 MW
Capacity
as recorded in REPD
Operational
Status
since 2001-10-01
Wind Onshore
Technology
CRE Energy/ Scottish Power
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted1998-04-20
Permission granted1999-04-28
12 months after submission
Operational2001-10-01
29 months after consent

Argyll and Bute’s record on onshore wind

Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute

Other built sites within 15 km

SiteMWDistance
Beinn an Tuirc Phase 2
Wind Onshore · Operational
43.71.4 km
Beinn an Tuirc
Wind Onshore · Operational
29.71.4 km
Beinn an Tuirc Windfarm Phase 3
Wind Onshore · Under Construction
49.94.7 km
Blary Hill Wind Farm
Wind Onshore · Operational
354.9 km
Deucheran Hill
Wind Onshore · Operational
15.85.7 km
Auchadaduie Wind Farm
Wind Onshore · Operational
6.97 km
Tangy Wind Farm/Tangy 1
Wind Onshore · Operational
12.811.3 km
Tangy Wind Farm Extension/Tangy 2
Wind Onshore · Operational
611.5 km

How big is Cnoc Donn Arnicle?

Cnoc Donn Arnicle has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cnoc Donn Arnicle?

REPD records the operator as CRE Energy/ Scottish Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cnoc Donn Arnicle approved and built?

The application was submitted on 1998-04-20. Permission was granted on 1999-04-28, 12 months later. The site became operational on 2001-10-01, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3294.