Novarly ParcelRenewable sites

Renewable sitesBlary Hill Wind Farm

Blary Hill Wind Farm

Blary Hill Wind Farm is operational in Argyll and Bute with a recorded capacity of 35 MW, and has been generating since 2022-01-01.

35 MW
Capacity
as recorded in REPD
Operational
Status
since 2022-01-01
Wind Onshore
Technology
Renewables Infrastructure Group / Renewable Energy Systems (RES)
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted2014-08-22
Permission granted2017-06-23
34 months after submission
Operational2022-01-01
54 months after consent

Argyll and Bute’s record on onshore wind

Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute

Other built sites within 15 km

SiteMWDistance
Auchadaduie Wind Farm
Wind Onshore · Operational
6.92.8 km
Beinn an Tuirc Windfarm Phase 3
Wind Onshore · Under Construction
49.93.2 km
Beinn an Tuirc
Wind Onshore · Operational
29.73.6 km
Beinn an Tuirc Phase 2
Wind Onshore · Operational
43.73.6 km
Cnoc Donn Arnicle
Wind Onshore · Operational
154.9 km
Tangy Wind Farm/Tangy 1
Wind Onshore · Operational
12.88.3 km
Deucheran Hill
Wind Onshore · Operational
15.89.2 km
Tangy Wind Farm Extension/Tangy 2
Wind Onshore · Operational
612.3 km

How big is Blary Hill Wind Farm?

Blary Hill Wind Farm has a recorded installed capacity of 35 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Blary Hill Wind Farm?

REPD records the operator as Renewables Infrastructure Group / Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Blary Hill Wind Farm approved and built?

The application was submitted on 2014-08-22. Permission was granted on 2017-06-23, 34 months later. The site became operational on 2022-01-01, 54 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4605.