Novarly ParcelRenewable sites

Renewable sitesAuchadaduie Wind Farm

Auchadaduie Wind Farm

Auchadaduie Wind Farm is operational in Argyll and Bute with a recorded capacity of 6.9 MW, and has been generating since 2018-11-21.

6.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-11-21
Wind Onshore
Technology
Fyne Futures
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted2012-01-18
Permission granted2014-07-21
30 months after submission
Operational2018-11-21
52 months after consent

Argyll and Bute’s record on onshore wind

Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute

Other built sites within 15 km

SiteMWDistance
Blary Hill Wind Farm
Wind Onshore · Operational
352.8 km
Beinn an Tuirc Windfarm Phase 3
Wind Onshore · Under Construction
49.93.1 km
Tangy Wind Farm/Tangy 1
Wind Onshore · Operational
12.85.5 km
Beinn an Tuirc
Wind Onshore · Operational
29.75.6 km
Beinn an Tuirc Phase 2
Wind Onshore · Operational
43.75.6 km
Cnoc Donn Arnicle
Wind Onshore · Operational
157 km
Tangy Wind Farm Extension/Tangy 2
Wind Onshore · Operational
611 km
Deucheran Hill
Wind Onshore · Operational
15.811.9 km

How big is Auchadaduie Wind Farm?

Auchadaduie Wind Farm has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Auchadaduie Wind Farm?

REPD records the operator as Fyne Futures. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Auchadaduie Wind Farm approved and built?

The application was submitted on 2012-01-18. Permission was granted on 2014-07-21, 30 months later. The site became operational on 2018-11-21, 52 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4184.

Novarly Parcel · official public data, read properly · parcel.novarly.com