Auchadaduie Wind Farm is an operational 6.9 MW onshore wind farm in Argyll and Bute, generating since 21 November 2018. Planning permission was granted on 21 July 2014, 30 months after submission. Operator of record: Fyne Futures.

6.9 MW
Capacity
as recorded in REPD
Operational
Status
since 21 November 2018
Wind Onshore
Technology
Fyne Futures
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted18 January 2012
Permission granted21 July 2014
30 months after submission
Operational21 November 2018
52 months after consent

Screening a site of your own?

RedlineUK · £39

Argyll and Bute approves 58% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Auchadaduie Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Argyll and Bute’s record on onshore wind

Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
352.8 km
Wind Onshore · Under Construction
49.93.1 km
Wind Onshore · Operational
12.85.5 km
Wind Onshore · Operational
43.75.6 km
Wind Onshore · Operational
29.75.6 km
Wind Onshore · Operational
157 km
Wind Onshore · Operational
611 km
Wind Onshore · Operational
15.811.9 km

How big is Auchadaduie Wind Farm?

Auchadaduie Wind Farm has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Auchadaduie Wind Farm?

REPD records the operator as Fyne Futures. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Auchadaduie Wind Farm approved and built?

The application was submitted on 18 January 2012. Permission was granted on 21 July 2014, 30 months later. The site became operational on 21 November 2018, 52 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4184.