Novarly ParcelRenewable sites

Renewable sitesSwinford Wind Farm

Swinford Wind Farm

Swinford Wind Farm is under construction in Harborough with a recorded capacity of 20 MW.

20 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Vattenfall
Harborough
Authority
England

Planning and build timeline

Application submitted2019-12-16
Permission granted2021-12-22
24 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Harborough’s record on solar

Harborough has decided 12 solar farms and approved 100%, taking a median of 2.5 months. See every solar farm decision in Harborough

Other built sites within 15 km

SiteMWDistance
Swinford Wind Farm
Wind Onshore · Operational
220.1 km
Lilbourne Wind Farm
Wind Onshore · Operational
101.9 km
Cotesbach Landfill Gas Project
Landfill Gas · Operational
2.33.3 km
Northfield House Solar Farm
Solar Photovoltaics · Operational
264.1 km
Yelvertoft Wind Farm
Wind Onshore · Operational
164.2 km
Crick Road
Solar Photovoltaics · Under Construction
49.96.1 km
Streetfield Farm
Solar Photovoltaics · Operational
18.36.9 km
M1 J18 Wind Turbines
Wind Onshore · Operational
46.9 km

How big is Swinford Wind Farm?

Swinford Wind Farm has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Swinford Wind Farm?

REPD records the operator as Vattenfall. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Swinford Wind Farm approved and built?

The application was submitted on 2019-12-16. Permission was granted on 2021-12-22, 24 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6720.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council