Renewable sites › Streetfield Farm
Streetfield Farm
Streetfield Farm is operational in Rugby with a recorded capacity of 18.3 MW, and has been generating since 2022-12-01.
Planning and build timeline
| Application submitted | 2019-02-07 |
| Permission granted | 2019-06-19 4 months after submission |
| Operational | 2022-12-01 41 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Rugby’s record on solar
Rugby has decided 19 solar farms and approved 95%, taking a median of 1.8 months. See every solar farm decision in Rugby →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Northfield House Solar Farm Solar Photovoltaics · Operational | 26 | 2.9 km |
Cotesbach Landfill Gas Project Landfill Gas · Operational | 2.3 | 3.6 km |
Swinford Wind Farm Wind Onshore · Operational | 22 | 6.8 km |
Swinford Wind Farm Solar Photovoltaics · Under Construction | 20 | 6.9 km |
Lilbourne Wind Farm Wind Onshore · Operational | 10 | 7.9 km |
Low Spinney Wind Farm Wind Onshore · Operational | 8 | 8.6 km |
Yelvertoft Wind Farm Wind Onshore · Operational | 16 | 10.2 km |
Ling Hall Solar Photovoltaics · Operational | 7 | 11.5 km |
How big is Streetfield Farm?
Streetfield Farm has a recorded installed capacity of 18.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Streetfield Farm?
REPD records the operator as Lightsource BP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Streetfield Farm approved and built?
The application was submitted on 2019-02-07. Permission was granted on 2019-06-19, 4 months later. The site became operational on 2022-12-01, 41 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7258.
Novarly Parcel · official public data, read properly · parcel.novarly.com