Renewable sitesStreetfield Farm

Streetfield Farm

Streetfield Farm is operational in Rugby with a recorded capacity of 18.3 MW, and has been generating since 2022-12-01.

18.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2022-12-01
Solar Photovoltaics
Technology
Lightsource BP
Rugby
Authority
England

Planning and build timeline

Application submitted2019-02-07
Permission granted2019-06-19
4 months after submission
Operational2022-12-01
41 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Rugby’s record on solar

Rugby has decided 19 solar farms and approved 95%, taking a median of 1.8 months. See every solar farm decision in Rugby

Other built sites within 15 km

SiteMWDistance
Northfield House Solar Farm
Solar Photovoltaics · Operational
262.9 km
Cotesbach Landfill Gas Project
Landfill Gas · Operational
2.33.6 km
Swinford Wind Farm
Wind Onshore · Operational
226.8 km
Swinford Wind Farm
Solar Photovoltaics · Under Construction
206.9 km
Lilbourne Wind Farm
Wind Onshore · Operational
107.9 km
Low Spinney Wind Farm
Wind Onshore · Operational
88.6 km
Yelvertoft Wind Farm
Wind Onshore · Operational
1610.2 km
Ling Hall
Solar Photovoltaics · Operational
711.5 km

How big is Streetfield Farm?

Streetfield Farm has a recorded installed capacity of 18.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Streetfield Farm?

REPD records the operator as Lightsource BP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Streetfield Farm approved and built?

The application was submitted on 2019-02-07. Permission was granted on 2019-06-19, 4 months later. The site became operational on 2022-12-01, 41 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7258.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council