Solar planning in Harborough

Harborough has decided 12 solar farms and approved 100% of them, taking a median of 2.5 months to decide. Consented capacity: 56 MW. 4 applications still awaiting a decision.

100%
Approved
12 granted · 0 refused
2.5 mo
Median decision
UK 2.3 mo
56 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Harborough compares

Against the 298 UK authorities with 5+ solar decisions, Harborough sits in the 77th percentile for approval rate (7 points above the England average) and the 46th percentile for speed.

Decisions by year

35Approved — 2 (2015)215Approved — 1 (2020)120Approved — 1 (2021)121Approved — 2 (2022)222Approved — 1 (2023)123Approved — 2 (2024)224Approved — 2 (2025)225Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (18)

SchemeMWStatusDecided
L and R Storage, C & V Business Park - Solar Panels
Novalux Energy · 25/01600/PDN · 1.9 mo to decide
0.29Awaiting Construction2026-01-14
Lutterworth Grammar School, Bitteswell Road - Solar PV System
Lutterworth Grammar School and Community College · 25/01466/PDN · 1.8 mo to decide
0.3Awaiting Construction2025-12-16
Astley Grange Farm, Back Lane - Solar Panels
Unknown · 25/00686/PDN · 1.7 mo to decide
0.28Awaiting Construction2025-07-08
DP World, Unit 5110, Vulcan Way - Solar Photovoltaics
Rhombus Nine Limited · 24/01402/PDN · 1.8 mo to decide
0.58Awaiting Construction2024-12-19
The Robert Smyth School, Burnmill Road - Solar Panels
Robert Smyth Academy · 24/00255/FUL · 3.8 mo to decide
0.17Awaiting Construction2024-07-09
Old Station Yard, Station Road - Solar Panels
Private Client · 24/00691/FUL
0.35Application Submitted2024-06-20
The Robert Smyth School, Burnmill Road - Solar Panels
Robert Smyth Academy · 23/01452/PDN · 3.2 mo to decide
0.17Revised2024-01-09
Armstrong Logistics, Wellington Parkway - Solar panels
ABRDN (Investments Trust/Standard Life) · 23/01374/PDN · 1.8 mo to decide
0.53Awaiting Construction2023-11-08
Marlborough Drive, Fleckney - Solar Panels
Coba Europe Limited · 22/01441/PDN · 8.2 mo to decide
0.41Awaiting Construction2022-09-14
Lodge Farm - Solar Farm & Battery Storage
Elgin Energy ES Co Limited · 22/01133/FUL
Application Submitted2022-05-20
Wellington Parkway - Solar panels
GLP Uk Management Limited · 22/00755/PDN · 1.8 mo to decide
0.47Awaiting Construction2022-05-16
Swinford Wind Farm
Vattenfall · 19/01853/FUL · 24.2 mo to decide
20Under Construction2021-12-22
Northfield House Solar Farm
Lightsource BP · 20/01289/FUL · 3.1 mo to decide
26Operational2020-11-25
Sunnydale Solar Farm
British Solar Renewables · 15/01120/FUL · 3 mo to decide
4.8Revised2015-11-16
Land at Meadow Farm
Lightsource Renewable Energy · 15/01116/FUL · 2.6 mo to decide
5Operational2015-10-08
Land Off Ingarsby Lane
T J Coates Ltd · 15/00676/FUL · 2.5 mo to decide
2.1Operational2015-07-30
Theddingworth solar farm
Abbey Renewables · 14/00833/FUL
30Application Withdrawn2014-11-27
Fiona Cairns HQ - Solar Panels
Fiona Cairns
No Application Required

Does Harborough approve solar farms?

Yes — of the 12 solar farms Harborough has decided, 100% were approved (12 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Harborough?

The median time from application to decision is 2.5 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Harborough consented?

56 MW has been consented across 12 approved schemes. A further 4 applications awaits a decision.

Other technologies in Harborough

Battery storage in HarboroughOnshore wind in Harborough

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.