Stronelairg Wind Farm
Stronelairg Wind Farm is an operational 227.7 MW onshore wind farm in Scotland, generating since 11 December 2018. Planning permission was granted on 6 June 2014, 23 months after submission. Operator of record: Scottish and Southern Energy (SSE).
Planning and build timeline
| Application submitted | 29 June 2012 |
| Permission granted | 6 June 2014 23 months after submission |
| Operational | 11 December 2018 54 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Stronelairg Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Small Hydro · Operational | 2 | 7.1 km |
Large Hydro · Operational | 100 | 8.3 km |
Small Hydro · Operational | 3 | 10.7 km |
Wind Onshore · Operational | 110 | 10.8 km |
Wind Onshore · Operational | 69.5 | 12.3 km |
Battery · Operational | 49.9 | 12.4 km |
Large Hydro · Operational | 15 | 12.7 km |
Large Hydro · Operational | 5.2 | 13.4 km |
How big is Stronelairg Wind Farm?
Stronelairg Wind Farm has a recorded installed capacity of 227.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Stronelairg Wind Farm?
REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Stronelairg Wind Farm approved and built?
The application was submitted on 29 June 2012. Permission was granted on 6 June 2014, 23 months later. The site became operational on 11 December 2018, 54 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4597.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode