Novarly ParcelRenewable sites

Renewable sitesStronelairg Wind Farm

Stronelairg Wind Farm

Stronelairg Wind Farm is operational in Scottish Government (S36) with a recorded capacity of 227.7 MW, and has been generating since 2018-12-11.

227.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-12-11
Wind Onshore
Technology
Scottish and Southern Energy (SSE)
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2012-06-29
Permission granted2014-06-06
23 months after submission
Operational2018-12-11
54 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Garrogie Hydro Scheme
Small Hydro · Operational
27.1 km
Glendoe Hydro Scheme
Large Hydro · Operational
1008.3 km
River E Hydro Scheme
Small Hydro · Operational
310.7 km
Bhlaraidh (previously Balmacaan)
Wind Onshore · Operational
11010.8 km
Corriegarth
Wind Onshore · Operational
69.512.3 km
Torrdhuin, Auchteraw Battery Storage Facility
Battery · Operational
49.912.4 km
Livishie
Large Hydro · Operational
1512.7 km
Foyers Falls
Large Hydro · Operational
5.213.4 km

How big is Stronelairg Wind Farm?

Stronelairg Wind Farm has a recorded installed capacity of 227.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stronelairg Wind Farm?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stronelairg Wind Farm approved and built?

The application was submitted on 2012-06-29. Permission was granted on 2014-06-06, 23 months later. The site became operational on 2018-12-11, 54 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4597.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council