Renewable sites › Corriegarth
Corriegarth
Corriegarth is operational in Highland with a recorded capacity of 69.5 MW, and has been generating since 2016-09-30.
Planning and build timeline
| Application submitted | 2007-07-15 |
| Permission granted | 2015-04-02 93 months after submission |
| Operational | 2016-09-30 18 months after consent |
Highland’s record on onshore wind
Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
River E Hydro Scheme Small Hydro · Operational | 3 | 6.1 km |
Garrogie Hydro Scheme Small Hydro · Operational | 2 | 7.4 km |
Dunmaglass Wind Farm Wind Onshore · Operational | 94 | 9.3 km |
Foyers Falls Large Hydro · Operational | 5.2 | 10 km |
Aberarder Wind Farm Wind Onshore · Under Construction | 49.9 | 10.3 km |
Foyers Pumped Storage Hydroelectricity · Operational | 300 | 10.8 km |
Inverfarigaig Small Hydro · Operational | 4 | 11.5 km |
Stronelairg Wind Farm Wind Onshore · Operational | 227.7 | 12.3 km |
How big is Corriegarth?
Corriegarth has a recorded installed capacity of 69.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Corriegarth?
REPD records the operator as Greencoat Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Corriegarth approved and built?
The application was submitted on 2007-07-15. Permission was granted on 2015-04-02, 93 months later. The site became operational on 2016-09-30, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4664.
Novarly Parcel · official public data, read properly · parcel.novarly.com