Novarly ParcelRenewable sites

Renewable sitesRiver E Hydro Scheme

River E Hydro Scheme

River E Hydro Scheme is an operational 3 MW hydro scheme in Highland, generating since 1 November 2007. Planning permission was granted on 23 May 2005, 29 months after submission. Operator of record: RWE npower.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 1 November 2007
Small Hydro
Technology
RWE npower
Highland
Authority
Scotland

Planning and build timeline

Application submitted20 December 2002
Permission granted23 May 2005
29 months after submission
Operational1 November 2007
29 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Highland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with River E Hydro Scheme’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
23.6 km
Large Hydro · Operational
5.24.3 km
Pumped Storage Hydroelectricity · Operational
3005.2 km
Wind Onshore · Operational
69.56.1 km
Small Hydro · Operational
47.4 km
Wind Onshore · Operational
1108 km
Wind Onshore · Operational
227.710.7 km
Large Hydro · Operational
1511.9 km

How big is River E Hydro Scheme?

River E Hydro Scheme has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates River E Hydro Scheme?

REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was River E Hydro Scheme approved and built?

The application was submitted on 20 December 2002. Permission was granted on 23 May 2005, 29 months later. The site became operational on 1 November 2007, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 428.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode