Renewable sitesGarrogie Hydro Scheme

Garrogie Hydro Scheme

Garrogie Hydro Scheme is an operational 2 MW hydro scheme in Highland, generating since 1 March 2005. Planning permission was granted on 1 June 2003, 18 months after submission. Operator of record: RWE npower.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 March 2005
Small Hydro
Technology
RWE npower
Highland
Authority
Scotland

Planning and build timeline

Application submitted20 November 2001
Permission granted1 June 2003
18 months after submission
Operational1 March 2005
21 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Highland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Garrogie Hydro Scheme’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
33.6 km
Large Hydro · Operational
5.26.7 km
Wind Onshore · Operational
1107.1 km
Wind Onshore · Operational
227.77.1 km
Wind Onshore · Operational
69.57.4 km
Pumped Storage Hydroelectricity · Operational
3007.7 km
Small Hydro · Operational
410.6 km
Large Hydro · Operational
1510.7 km

How big is Garrogie Hydro Scheme?

Garrogie Hydro Scheme has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Garrogie Hydro Scheme?

REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Garrogie Hydro Scheme approved and built?

The application was submitted on 20 November 2001. Permission was granted on 1 June 2003, 18 months later. The site became operational on 1 March 2005, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 435.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode