Renewable sitesGlendoe Hydro Scheme

Glendoe Hydro Scheme

Glendoe Hydro Scheme is operational in Scottish Government (S36) with a recorded capacity of 100 MW, and has been generating since 2008-12-01.

100 MW
Capacity
as recorded in REPD
Operational
Status
since 2008-12-01
Large Hydro
Technology
Scottish and Southern Energy (SSE)
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2003-05-01
Permission granted2005-07-28
27 months after submission
Operational2008-12-01
40 months after consent

Other built sites within 15 km

SiteMWDistance
Torrdhuin, Auchteraw Battery Storage Facility
Battery · Operational
49.94.6 km
Great Glen Scheme
Large Hydro · Operational
367.5 km
Stronelairg Wind Farm
Wind Onshore · Operational
227.78.3 km
Livishie
Large Hydro · Operational
158.6 km
Bhlaraidh (previously Balmacaan)
Wind Onshore · Operational
1109.6 km
Invergarry
Large Hydro · Operational
2010.6 km
Garrogie Hydro Scheme
Small Hydro · Operational
211.7 km
Millennium Extension II
Wind Onshore · Operational
1513.6 km

How big is Glendoe Hydro Scheme?

Glendoe Hydro Scheme has a recorded installed capacity of 100 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Glendoe Hydro Scheme?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Glendoe Hydro Scheme approved and built?

The application was submitted on 2003-05-01. Permission was granted on 2005-07-28, 27 months later. The site became operational on 2008-12-01, 40 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 388.