Novarly ParcelRenewable sites

Renewable sitesBraes O'Doune

Braes O'Doune

Braes O'Doune is an operational 72 MW onshore wind farm in Scotland, generating since 1 September 2006. Planning permission was granted on 5 October 2004, 23 months after submission. Operator of record: Greencoat UK Wind.

72 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2006
Wind Onshore
Technology
Greencoat UK Wind
National
Authority
Scotland

Planning and build timeline

Application submitted31 October 2002
Permission granted5 October 2004
23 months after submission
Operational1 September 2006
23 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Braes O'Doune’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Under Construction
20.78.9 km
Small Hydro · Operational
411.6 km
Small Hydro · Operational
312.3 km

How big is Braes O'Doune?

Braes O'Doune has a recorded installed capacity of 72 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Braes O'Doune?

REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Braes O'Doune approved and built?

The application was submitted on 31 October 2002. Permission was granted on 5 October 2004, 23 months later. The site became operational on 1 September 2006, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3119.