Renewable sites › Tythegston Landfill Site
Tythegston Landfill Site
Tythegston Landfill Site is an operational 1.2 MW landfill gas site in Bridgend, generating since 1 October 1998. Planning permission was granted on 4 September 1997, 2 months after submission. Operator of record: Renewable Power Generation Ltd.
Planning and build timeline
| Application submitted | 1 July 1997 |
| Permission granted | 4 September 1997 2 months after submission |
| Operational | 1 October 1998 13 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Bridgend: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Tythegston Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 5 | 1.1 km |
Anaerobic Digestion · Operational | 3 | 1.6 km |
Wind Onshore · Operational | 2.5 | 1.6 km |
Solar Photovoltaics · Operational | 3.8 | 2 km |
Solar Photovoltaics · Operational | 1.7 | 2.7 km |
Solar Photovoltaics · Operational | 15 | 3.9 km |
Solar Photovoltaics · Operational | 3.8 | 5.7 km |
Solar Photovoltaics · Under Construction | 0.8 | 8.7 km |
How big is Tythegston Landfill Site?
Tythegston Landfill Site has a recorded installed capacity of 1.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tythegston Landfill Site?
REPD records the operator as Renewable Power Generation Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tythegston Landfill Site approved and built?
The application was submitted on 1 July 1997. Permission was granted on 4 September 1997, 2 months later. The site became operational on 1 October 1998, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 604.