Novarly ParcelRenewable sites

Renewable sitesSeaview Farm

Seaview Farm

Seaview Farm is operational in Bridgend with a recorded capacity of 1.7 MW, and has been generating since 2016-03-30.

1.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-30
Solar Photovoltaics
Technology
Private Developer
Bridgend
Authority
Wales

Planning and build timeline

Application submitted2014-03-05
Permission granted2014-06-11
3 months after submission
Operational2016-03-30
22 months after consent

Bridgend’s record on solar

Bridgend has decided 6 solar farms and approved 100%, taking a median of 3.5 months. See every solar farm decision in Bridgend

Other built sites within 15 km

SiteMWDistance
Newton Down
Wind Onshore · Operational
52 km
Stormy Down (Waste AD)
Anaerobic Digestion · Operational
32.1 km
Parc Stormy, Stormy Down
Wind Onshore · Operational
2.52.2 km
Stormy Down Solar Farm
Solar Photovoltaics · Operational
3.82.5 km
Tythegston Landfill Site
Landfill Gas · Operational
1.22.7 km
Caergarw Farm
Solar Photovoltaics · Operational
3.85 km
Court Colman solar park
Solar Photovoltaics · Operational
156.1 km
Longlands Lane
Wind Onshore · Operational
1.58.4 km

How big is Seaview Farm?

Seaview Farm has a recorded installed capacity of 1.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Seaview Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Seaview Farm approved and built?

The application was submitted on 2014-03-05. Permission was granted on 2014-06-11, 3 months later. The site became operational on 2016-03-30, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1787.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council