Stonish Hill (Bilsthorpe) is operational in Newark and Sherwood with a recorded capacity of 10.3 MW, and has been generating since 2013-03-31.

10.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-31
Wind Onshore
Technology
REG Power Management (John Laing/Peel Energy)
Newark and Sherwood
Authority
England

Planning and build timeline

Application submitted2007-06-08
Permission granted2009-03-16
21 months after submission
Operational2013-03-31
48 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Newark and Sherwood’s record on onshore wind

Newark and Sherwood has decided 5 onshore wind schemes and approved 60%, taking a median of 15.4 months. See every onshore wind scheme decision in Newark and Sherwood

Other built sites within 15 km

SiteMWDistance
Eakring Solar Farm
Solar Photovoltaics · Operational
11.90.4 km
Cheesecake Energy Air Energy Storage
Compressed Air Energy Storage · Operational
1 km
Stud Farm, Rufford (Farm AD)
Anaerobic Digestion · Operational
2.21.2 km
Bilsthorpe Quarry Solar Park
Solar Photovoltaics · Operational
4.81.2 km
Bilsthorpe (Land off Forest Lane)
Solar Photovoltaics · Operational
53.2 km
Rufford Lane
Solar Photovoltaics · Operational
2.64.1 km
Land South Off Ollerton Road
Solar Photovoltaics · Operational
4.24.9 km
Lindhurst Wind Farm
Wind Onshore · Operational
159.9 km

How big is Stonish Hill (Bilsthorpe)?

Stonish Hill (Bilsthorpe) has a recorded installed capacity of 10.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stonish Hill (Bilsthorpe)?

REPD records the operator as REG Power Management (John Laing/Peel Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stonish Hill (Bilsthorpe) approved and built?

The application was submitted on 2007-06-08. Permission was granted on 2009-03-16, 21 months later. The site became operational on 2013-03-31, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3739.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council