Novarly ParcelRenewable planning

Renewable planning Onshore windNewark and Sherwood

Onshore wind planning in Newark and Sherwood

Newark and Sherwood has decided 5 onshore wind schemes and approved 60% of them, taking a median of 15.4 months to decide. Consented capacity: 34 MW. 2 applications still awaiting a decision.

60%
Approved
3 granted · 2 refused
15.4 mo
Median decision
UK 11.5 mo
34 MW
Consented
11 MW refused
4
Appeals
2 allowed on appeal

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Newark and Sherwood compares

Against the 75 UK authorities with 5+ onshore wind decisions, Newark and Sherwood sits in the 31st percentile for approval rate (8 points below the England average) and the 41st percentile for speed.

Decisions by year

35Approved — 1 (2014)Refused — 1 (2014)214Refused — 1 (2015)115
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (8)

SchemeMWStatusDecided
Trentholme Farm, North Clifton - Wind Turbine
P & A Croft (Farmers) Limited · 26/00098/FUL
0.22Application Submitted2026-01-21
Newark Sugar Factory
British Sugar Plc · 15/01228/FULM
1.5Application Withdrawn2015-09-14
South East of Wadnal Lane
Caddick Renewables Ltd · 14/00837/FUL · 13.3 mo to decide
1.3Appeal Refused2015-06-29
Fox Covert Wind Farm
Wind Prospect Developments · 13/00889/FULM · 15.2 mo to decide
10Application Refused2014-10-09
Hawton Wind Farm
Temporis Capital · 11/01588/FULM · 33.8 mo to decide
9Operational2014-09-29
Stonish Hill (Bilsthorpe)
REG Power Management (John Laing/Peel Energy) · 07/00856/FULEIA · 21.3 mo to decide
10.3Operational2009-03-16
Lindhurst Wind Farm
Npower Renewables · 06/01014/FULM · 15.7 mo to decide
15Operational2007-09-21
Stonish Hill
Harworth Power · 11 mo to decide
14Revised2006-11-01

Does Newark and Sherwood approve onshore wind schemes?

Yes — of the 5 onshore wind schemes Newark and Sherwood has decided, 60% were approved (3 granted, 2 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Newark and Sherwood?

The median time from application to decision is 15.4 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Newark and Sherwood consented?

34 MW has been consented across 3 approved schemes, with 11 MW refused. A further 2 applications awaits a decision.

Other technologies in Newark and Sherwood

Solar in Newark and SherwoodBattery storage in Newark and Sherwood

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com