Bilsthorpe Quarry Solar Park is an operational 4.8 MW solar farm in Newark and Sherwood, generating since 18 November 2014. Planning permission was granted on 12 August 2013, 8 months after submission. Operator of record: Anesco.

4.8 MW
Capacity
as recorded in REPD
Operational
Status
since 18 November 2014
Solar Photovoltaics
Technology
Anesco
Newark and Sherwood
Authority
England

Planning and build timeline

Application submitted5 December 2012
Permission granted12 August 2013
8 months after submission
Operational18 November 2014
15 months after consent

Screening a site of your own?

RedlineUK · £39

Newark and Sherwood approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bilsthorpe Quarry Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Newark and Sherwood’s record on solar

Newark and Sherwood has decided 25 solar farms and approved 96%, taking a median of 4.9 months. See every solar farm decision in Newark and Sherwood

Other built sites within 15 km

SiteMWDistance
Compressed Air Energy Storage · Operational
0.4 km
Wind Onshore · Operational
10.31.2 km
Solar Photovoltaics · Operational
11.91.6 km
Anaerobic Digestion · Operational
2.21.8 km
Solar Photovoltaics · Operational
52 km
Solar Photovoltaics · Operational
2.65.3 km
Solar Photovoltaics · Operational
4.25.4 km
Wind Onshore · Operational
158.9 km

How big is Bilsthorpe Quarry Solar Park?

Bilsthorpe Quarry Solar Park has a recorded installed capacity of 4.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bilsthorpe Quarry Solar Park?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bilsthorpe Quarry Solar Park approved and built?

The application was submitted on 5 December 2012. Permission was granted on 12 August 2013, 8 months later. The site became operational on 18 November 2014, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2378.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode