Renewable sites › Stud Farm, Rufford (Farm AD)
Stud Farm, Rufford (Farm AD)
Stud Farm, Rufford (Farm AD) is operational in Newark and Sherwood with a recorded capacity of 2.2 MW, and has been generating since 2017-03-30.
Planning and build timeline
| Application submitted | 2009-09-28 |
| Permission granted | 2010-07-05 9 months after submission |
| Operational | 2017-03-30 81 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Eakring Solar Farm Solar Photovoltaics · Operational | 11.9 | 1 km |
Stonish Hill (Bilsthorpe) Wind Onshore · Operational | 10.3 | 1.2 km |
Cheesecake Energy Air Energy Storage Compressed Air Energy Storage · Operational | — | 1.4 km |
Bilsthorpe Quarry Solar Park Solar Photovoltaics · Operational | 4.8 | 1.8 km |
Bilsthorpe (Land off Forest Lane) Solar Photovoltaics · Operational | 5 | 3.6 km |
Rufford Lane Solar Photovoltaics · Operational | 2.6 | 3.6 km |
Land South Off Ollerton Road Solar Photovoltaics · Operational | 4.2 | 3.7 km |
Netherfield Lane Solar Photovoltaics · Operational | 19.7 | 9.1 km |
How big is Stud Farm, Rufford (Farm AD)?
Stud Farm, Rufford (Farm AD) has a recorded installed capacity of 2.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Stud Farm, Rufford (Farm AD)?
REPD records the operator as Future Biogas. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Stud Farm, Rufford (Farm AD) approved and built?
The application was submitted on 2009-09-28. Permission was granted on 2010-07-05, 9 months later. The site became operational on 2017-03-30, 81 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 265.