Renewable sites › Staythorpe Road - Battery energy storage
Staythorpe Road - Battery energy storage
Staythorpe Road - Battery energy storage is under construction in Newark and Sherwood with a recorded capacity of 360 MW.
Planning and build timeline
| Application submitted | 2022-11-23 |
| Permission granted | 2024-05-03 17 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Newark and Sherwood’s record on battery storage
Newark and Sherwood has decided 6 battery storage schemes and approved 100%, taking a median of 12 months. See every battery storage scheme decision in Newark and Sherwood →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
The Grange Solar Photovoltaics · Operational | 49.9 | 4.3 km |
Hawton Wind Farm Wind Onshore · Operational | 9 | 4.9 km |
Balderton Biomass (dedicated) · Operational | 20.3 | 5.1 km |
Grange Solar Farm Solar Photovoltaics · Operational | 4.6 | 6.7 km |
Copley Farm Solar Photovoltaics · Operational | 30 | 10.8 km |
Stonish Hill (Bilsthorpe) Wind Onshore · Operational | 10.3 | 12.8 km |
Bilsthorpe Quarry Solar Park Solar Photovoltaics · Operational | 4.8 | 12.8 km |
Lodge Farm - Orston Solar Photovoltaics · Operational | 12.4 | 13 km |
How big is Staythorpe Road - Battery energy storage?
Staythorpe Road - Battery energy storage has a recorded installed capacity of 360 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Staythorpe Road - Battery energy storage?
REPD records the operator as Ecap Renewables (Elements Green). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Staythorpe Road - Battery energy storage approved and built?
The application was submitted on 2022-11-23. Permission was granted on 2024-05-03, 17 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11321.