Renewable sites › Standby Embedded Stor Power Plant - Battery storage
Standby Embedded Stor Power Plant - Battery storage
Standby Embedded Stor Power Plant - Battery storage is under construction in North Tyneside with a recorded capacity of 20 MW.
Planning and build timeline
| Application submitted | 2021-04-22 |
| Permission granted | 2021-06-16 2 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Tynemouth Energy Storage System (TESS) Battery · Operational | 25 | 2.8 km |
Howdon STW Sewage Sludge Digestion · Operational | 6 | 3.2 km |
Port of Tyne Battery · Operational | 35 | 3.4 km |
Seghill Village Waste Disposal Site phase 1 and 2 Landfill Gas · Operational | 4.1 | 7.4 km |
Regent Street - Solar Photovoltaic Panels Solar Photovoltaics · Operational | — | 9.2 km |
Nissan Test Track Solar Photovoltaics · Operational | 4.8 | 9.3 km |
Unipres building Solar Photovoltaics · Operational | 4.9 | 9.5 km |
Nissan Wind Farm Wind Onshore · Operational | 4 | 10 km |
How big is Standby Embedded Stor Power Plant - Battery storage?
Standby Embedded Stor Power Plant - Battery storage has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Standby Embedded Stor Power Plant - Battery storage?
REPD records the operator as Green Frog Power 214 Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Standby Embedded Stor Power Plant - Battery storage approved and built?
The application was submitted on 2021-04-22. Permission was granted on 2021-06-16, 2 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9010.