Novarly ParcelRenewable sites

Renewable sitesColdham Hall

Coldham Hall

Coldham Hall is operational in Fenland with a recorded capacity of 14 MW, and has been generating since 2005-08-01.

14 MW
Capacity
as recorded in REPD
Operational
Status
since 2005-08-01
Wind Onshore
Technology
Co-op
Fenland
Authority
England

Planning and build timeline

Application submitted2002-01-25
Permission granted2002-10-26
9 months after submission
Operational2005-08-01
33 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fenland’s record on onshore wind

Fenland has decided 20 onshore wind schemes and approved 85%, taking a median of 12.8 months. See every onshore wind scheme decision in Fenland

Other built sites within 15 km

SiteMWDistance
Coldham
Wind Onshore · Operational
161.5 km
Whitemill Wind Farm
Wind Onshore · Operational
142.1 km
MARCH SEWAGE TREATMENT WORKS - WIND TURBINE
Wind Onshore · Operational
23.5 km
Stags Holt Extension
Wind Onshore · Operational
23.7 km
Stags Holt
Wind Onshore · Operational
183.7 km
Long Hill Road
Wind Onshore · Operational
23.7 km
Wisbech Solar Farm
Solar Photovoltaics · Operational
3.55 km
Fenmarc Fenland AD Plant (Waste AD)
Anaerobic Digestion · Operational
1.55.3 km

How big is Coldham Hall?

Coldham Hall has a recorded installed capacity of 14 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Coldham Hall?

REPD records the operator as Co-op. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Coldham Hall approved and built?

The application was submitted on 2002-01-25. Permission was granted on 2002-10-26, 9 months later. The site became operational on 2005-08-01, 33 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3479.

Novarly Parcel · official public data, read properly · parcel.novarly.com