Renewable sites › Long Hill Road
Long Hill Road
Long Hill Road is operational in Fenland with a recorded capacity of 2 MW, and has been generating since 2005-01-01.
Planning and build timeline
| Application submitted | 2001-07-03 |
| Permission granted | 2003-04-07 21 months after submission |
| Operational | 2005-01-01 21 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Fenland’s record on onshore wind
Fenland has decided 20 onshore wind schemes and approved 85%, taking a median of 12.8 months. See every onshore wind scheme decision in Fenland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Fenmarc Fenland AD Plant (Waste AD) Anaerobic Digestion · Operational | 1.5 | 1.9 km |
MARCH SEWAGE TREATMENT WORKS - WIND TURBINE Wind Onshore · Operational | 2 | 2.2 km |
Stags Holt Wind Onshore · Operational | 18 | 2.3 km |
Stags Holt Extension Wind Onshore · Operational | 2 | 2.3 km |
Coldham Wind Onshore · Operational | 16 | 2.7 km |
Coldham Hall Wind Onshore · Operational | 14 | 3.7 km |
Whitemill Wind Farm Wind Onshore · Operational | 14 | 4.1 km |
Boardinghouse Wind Farm Wind Onshore · Operational | 10.3 | 4.7 km |
How big is Long Hill Road?
Long Hill Road has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Long Hill Road?
REPD records the operator as Snow Mountain Investment Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Long Hill Road approved and built?
The application was submitted on 2001-07-03. Permission was granted on 2003-04-07, 21 months later. The site became operational on 2005-01-01, 21 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3101.
Novarly Parcel · official public data, read properly · parcel.novarly.com