Novarly ParcelRenewable sites

Renewable sitesSt Columb Major Solar Farm

St Columb Major Solar Farm

St Columb Major Solar Farm is an operational 7 MW solar farm in Cornwall, generating since 14 March 2014. Planning permission was granted on 28 April 2011, 3 months after submission. Operator of record: Inazin Solar (previoulsy owned by Low Carbon Solar).

7 MW
Capacity
as recorded in REPD
Operational
Status
since 14 March 2014
Solar Photovoltaics
Technology
Inazin Solar (previoulsy owned by Low Carbon Solar)
Cornwall
Authority
England

Planning and build timeline

Application submitted27 January 2011
Permission granted28 April 2011
3 months after submission
Operational14 March 2014
35 months after consent

Screening a site of your own?

RedlineUK · £39

Cornwall approves 92% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with St Columb Major Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on solar

Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
3.84.4 km
Wind Onshore · Operational
105.4 km
Solar Photovoltaics · Operational
1.55.5 km
Solar Photovoltaics · Operational
55.6 km
Wind Onshore · Operational
9.85.6 km
Solar Photovoltaics · Operational
1.15.9 km
EfW Incineration · Operational
206.2 km
Solar Photovoltaics · Operational
56.6 km

How big is St Columb Major Solar Farm?

St Columb Major Solar Farm has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates St Columb Major Solar Farm?

REPD records the operator as Inazin Solar (previoulsy owned by Low Carbon Solar). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was St Columb Major Solar Farm approved and built?

The application was submitted on 27 January 2011. Permission was granted on 28 April 2011, 3 months later. The site became operational on 14 March 2014, 35 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1566.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode