Renewable sites › Denzell Downs Wind Farm
Denzell Downs Wind Farm
Denzell Downs Wind Farm is operational in Cornwall with a recorded capacity of 10 MW, and has been generating since 2015-11-24.
Planning and build timeline
| Application submitted | 2013-06-27 |
| Permission granted | 2013-12-12 6 months after submission |
| Operational | 2015-11-24 23 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cornwall’s record on onshore wind
Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bears Down Wind Farm Wind Onshore · Operational | 9.8 | 0.6 km |
Winnards Perch Solar Farm Solar Photovoltaics · Operational | 3.8 | 3 km |
Trenouth Farm Solar Photovoltaics · Operational | 3.6 | 3.2 km |
Trelow Farm Solar Photovoltaics · Operational | 1.6 | 3.5 km |
Kernow Solar Farm Solar Photovoltaics · Operational | 5 | 5.1 km |
St Columb Major Solar Farm Solar Photovoltaics · Operational | 7 | 5.4 km |
Hawksland Solar Solar Photovoltaics · Operational | 3.1 | 6.4 km |
Middle Treworder Farm Solar Photovoltaics · Operational | 5 | 9.4 km |
How big is Denzell Downs Wind Farm?
Denzell Downs Wind Farm has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Denzell Downs Wind Farm?
REPD records the operator as REG Windpower / BlackRock. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Denzell Downs Wind Farm approved and built?
The application was submitted on 2013-06-27. Permission was granted on 2013-12-12, 6 months later. The site became operational on 2015-11-24, 23 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4651.