Trefullock Solar Farm is an operational 5 MW solar farm in Cornwall, generating since 7 July 2011. Planning permission was granted on 7 January 2011, 3 months after submission. Operator of record: Bosch Solar Energy.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 7 July 2011
Solar Photovoltaics
Technology
Bosch Solar Energy
Cornwall
Authority
England

Planning and build timeline

Application submitted20 October 2010
Permission granted7 January 2011
3 months after submission
Operational7 July 2011
6 months after consent

Screening a site of your own?

RedlineUK · £39

Cornwall approves 92% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Trefullock Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on solar

Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.10.8 km
Solar Photovoltaics · Operational
101 km
Solar Photovoltaics · Operational
1.51.1 km
Wind Onshore · Operational
11.9 km
Solar Photovoltaics · Operational
53.4 km
Solar Photovoltaics · Operational
124 km
Solar Photovoltaics · Operational
4.84.3 km
Solar Photovoltaics · Operational
74.4 km

How big is Trefullock Solar Farm?

Trefullock Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Trefullock Solar Farm?

REPD records the operator as Bosch Solar Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Trefullock Solar Farm approved and built?

The application was submitted on 20 October 2010. Permission was granted on 7 January 2011, 3 months later. The site became operational on 7 July 2011, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1080.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode