Renewable sites › PG1-Coxhoe Waste Disposal Site
PG1-Coxhoe Waste Disposal Site
PG1-Coxhoe Waste Disposal Site is an operational 3.8 MW landfill gas site in County Durham, generating since 1 April 1998. Planning permission was granted on 24 April 1997, 2 months after submission. Operator of record: Durham County Waste Management Company.
Planning and build timeline
| Application submitted | 6 March 1997 |
| Permission granted | 24 April 1997 2 months after submission |
| Operational | 1 April 1998 11 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in County Durham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with PG1-Coxhoe Waste Disposal Site’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 5.2 | 3.2 km |
Wind Onshore · Operational | 5.2 | 3.7 km |
Wind Onshore · Operational | 1.3 | 6.5 km |
Wind Onshore · Operational | 2.7 | 6.5 km |
Wind Onshore · Operational | 10 | 7.1 km |
Biomass (dedicated) · Operational | 18 | 7.9 km |
Wind Onshore · Operational | 4 | 8.1 km |
Wind Onshore · Operational | 20.5 | 9.1 km |
How big is PG1-Coxhoe Waste Disposal Site?
PG1-Coxhoe Waste Disposal Site has a recorded installed capacity of 3.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates PG1-Coxhoe Waste Disposal Site?
REPD records the operator as Durham County Waste Management Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was PG1-Coxhoe Waste Disposal Site approved and built?
The application was submitted on 6 March 1997. Permission was granted on 24 April 1997, 2 months later. The site became operational on 1 April 1998, 11 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 563.