Renewable sites › Haswell Moor
Haswell Moor
Haswell Moor is operational in County Durham with a recorded capacity of 10 MW, and has been generating since 2010-12-12.
Planning and build timeline
| Application submitted | 2006-11-23 |
| Permission granted | 2007-12-18 13 months after submission |
| Operational | 2010-12-12 36 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
County Durham’s record on onshore wind
County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hare Hill (B) Wind Onshore · Operational | 2.7 | 0.6 km |
Hare Hill Wind Onshore · Operational | 1.3 | 0.6 km |
High Haswell Wind Farm Wind Onshore · Operational | 4 | 2.8 km |
Peterlee Solar Farm Solar Photovoltaics · Operational | 5 | 3 km |
B H K UK Davy Drive - Solar Panels Solar Photovoltaics · Under Construction | 1.34 | 3.1 km |
Hawthorn Grid Site - Battery Storage Battery · Operational | 49 | 4.1 km |
Southern Law Wind Onshore · Operational | 5.2 | 5.1 km |
Trimdon Grange Wind Onshore · Operational | 5.2 | 5.5 km |
How big is Haswell Moor?
Haswell Moor has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Haswell Moor?
REPD records the operator as E.ON UK Renewables Developments Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Haswell Moor approved and built?
The application was submitted on 2006-11-23. Permission was granted on 2007-12-18, 13 months later. The site became operational on 2010-12-12, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3507.