Novarly ParcelRenewable sites

Renewable sitesSouth Sharpley Wind Farm (Revised)

South Sharpley Wind Farm (Revised)

South Sharpley Wind Farm (Revised) is operational in County Durham with a recorded capacity of 7.5 MW, and has been generating since 2013-01-23.

7.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-01-23
Wind Onshore
Technology
REG Windpower (previously Cornwall Light & Power)
County Durham
Authority
England

Planning and build timeline

Application submitted2008-05-01
Permission granted2011-04-10
35 months after submission
Operational2013-01-23
21 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on onshore wind

County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham

Other built sites within 15 km

SiteMWDistance
Great Eppleton Farm Repowering
Wind Onshore · Operational
8.22.2 km
Great Eppleton Wind Farm
Wind Onshore · Operational
32.2 km
Houghton-le-Spring Landfill Site
Landfill Gas · Operational
33.2 km
High Sharpley Wind Farm
Wind Onshore · Operational
2.64.2 km
Hawthorn Grid Site - Battery Storage
Battery · Operational
494.4 km
Sedgeletch Sewage Treatment Works
Solar Photovoltaics · Under Construction
6.2 km
High Haswell Wind Farm
Wind Onshore · Operational
46.2 km
Peterlee Solar Farm
Solar Photovoltaics · Operational
57.6 km

How big is South Sharpley Wind Farm (Revised)?

South Sharpley Wind Farm (Revised) has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates South Sharpley Wind Farm (Revised)?

REPD records the operator as REG Windpower (previously Cornwall Light & Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was South Sharpley Wind Farm (Revised) approved and built?

The application was submitted on 2008-05-01. Permission was granted on 2011-04-10, 35 months later. The site became operational on 2013-01-23, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3985.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council