South Sharpley Wind Farm (Revised) is an operational 7.5 MW onshore wind farm in County Durham, generating since 23 January 2013. Planning permission was granted on 10 April 2011, 35 months after submission. Operator of record: REG Windpower (previously Cornwall Light & Power).

7.5 MW
Capacity
as recorded in REPD
Operational
Status
since 23 January 2013
Wind Onshore
Technology
REG Windpower (previously Cornwall Light & Power)
County Durham
Authority
England

Planning and build timeline

Application submitted1 May 2008
Permission granted10 April 2011
35 months after submission
Operational23 January 2013
21 months after consent

Screening a site of your own?

RedlineUK · £39

County Durham approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with South Sharpley Wind Farm (Revised)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on onshore wind

County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
32.2 km
Wind Onshore · Operational
8.22.2 km
Landfill Gas · Operational
33.2 km
Wind Onshore · Operational
2.64.2 km
Battery · Operational
494.4 km
Solar Photovoltaics · Under Construction
6.2 km
Wind Onshore · Operational
46.2 km
Solar Photovoltaics · Operational
57.6 km

How big is South Sharpley Wind Farm (Revised)?

South Sharpley Wind Farm (Revised) has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates South Sharpley Wind Farm (Revised)?

REPD records the operator as REG Windpower (previously Cornwall Light & Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was South Sharpley Wind Farm (Revised) approved and built?

The application was submitted on 1 May 2008. Permission was granted on 10 April 2011, 35 months later. The site became operational on 23 January 2013, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3985.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode