Peterlee Solar Farm is an operational 5 MW solar farm in County Durham, generating since 30 March 2016. Planning permission was granted on 14 January 2016, 6 months after submission. Operator of record: Zaravolt Development.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 30 March 2016
Solar Photovoltaics
Technology
Zaravolt Development
County Durham
Authority
England

Planning and build timeline

Application submitted23 July 2015
Permission granted14 January 2016
6 months after submission
Operational30 March 2016
2 months after consent

Screening a site of your own?

RedlineUK · £39

County Durham approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Peterlee Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on solar

County Durham has decided 46 solar farms and approved 93%, taking a median of 2 months. See every solar farm decision in County Durham

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
1.340.7 km
Wind Onshore · Operational
103 km
Battery · Operational
493.4 km
Wind Onshore · Operational
2.73.5 km
Wind Onshore · Operational
1.33.5 km
Wind Onshore · Operational
44.4 km
Wind Onshore · Operational
8.27 km
Wind Onshore · Operational
37 km

How big is Peterlee Solar Farm?

Peterlee Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Peterlee Solar Farm?

REPD records the operator as Zaravolt Development. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Peterlee Solar Farm approved and built?

The application was submitted on 23 July 2015. Permission was granted on 14 January 2016, 6 months later. The site became operational on 30 March 2016, 2 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5694.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode