High Haswell Wind Farm

High Haswell Wind Farm is an operational 4 MW onshore wind farm in County Durham, generating since 10 March 2011. Planning permission was granted on 18 December 2007, 9 months after submission. Operator of record: Hallam Land Management.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 10 March 2011
Wind Onshore
Technology
Hallam Land Management
County Durham
Authority
England

Planning and build timeline

Application submitted3 April 2007
Permission granted18 December 2007
9 months after submission
Operational10 March 2011
39 months after consent

Screening a site of your own?

RedlineUK · £39

County Durham approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with High Haswell Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on onshore wind

County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
102.8 km
Battery · Operational
492.8 km
Wind Onshore · Operational
2.73.1 km
Wind Onshore · Operational
1.33.1 km
Wind Onshore · Operational
34.4 km
Wind Onshore · Operational
8.24.4 km
Solar Photovoltaics · Operational
54.4 km
Solar Photovoltaics · Under Construction
1.344.9 km

How big is High Haswell Wind Farm?

High Haswell Wind Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates High Haswell Wind Farm?

REPD records the operator as Hallam Land Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was High Haswell Wind Farm approved and built?

The application was submitted on 3 April 2007. Permission was granted on 18 December 2007, 9 months later. The site became operational on 10 March 2011, 39 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3050.