Solar Farm at Fields Farm (Phase 1)

Solar Farm at Fields Farm (Phase 1) is an operational 5 MW solar farm in Stratford-on-Avon, generating since 23 March 2016. Planning permission was granted on 29 June 2015, 3 months after submission. Operator of record: Foresight Group (TGC Renewables).

5 MW
Capacity
as recorded in REPD
Operational
Status
since 23 March 2016
Solar Photovoltaics
Technology
Foresight Group (TGC Renewables)
Stratford-on-Avon
Authority
England

Planning and build timeline

Application submitted16 March 2015
Permission granted29 June 2015
3 months after submission
Operational23 March 2016
9 months after consent

Screening a site of your own?

RedlineUK · £39

Stratford-on-Avon approves 94% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Solar Farm at Fields Farm (Phase 1)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Stratford-on-Avon’s record on solar

Stratford-on-Avon has decided 36 solar farms and approved 94%, taking a median of 3.7 months. See every solar farm decision in Stratford-on-Avon

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
0.51.1 km
Solar Photovoltaics · Under Construction
34.81.4 km
Battery · Under Construction
1.4 km
Landfill Gas · Operational
12.3 km
Solar Photovoltaics · Operational
2.13 km
Solar Photovoltaics · Operational
10.44.2 km
Solar Photovoltaics · Operational
104.9 km
Solar Photovoltaics · Operational
49.95.5 km

How big is Solar Farm at Fields Farm (Phase 1)?

Solar Farm at Fields Farm (Phase 1) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Solar Farm at Fields Farm (Phase 1)?

REPD records the operator as Foresight Group (TGC Renewables). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Solar Farm at Fields Farm (Phase 1) approved and built?

The application was submitted on 16 March 2015. Permission was granted on 29 June 2015, 3 months later. The site became operational on 23 March 2016, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5244.