Renewable sites › Solar Farm at Fields Farm (Phase 1)
Solar Farm at Fields Farm (Phase 1)
Solar Farm at Fields Farm (Phase 1) is operational in Stratford-on-Avon with a recorded capacity of 5 MW, and has been generating since 2016-03-23.
Planning and build timeline
| Application submitted | 2015-03-16 |
| Permission granted | 2015-06-29 3 months after submission |
| Operational | 2016-03-23 9 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Stratford-on-Avon’s record on solar
Stratford-on-Avon has decided 36 solar farms and approved 94%, taking a median of 3.7 months. See every solar farm decision in Stratford-on-Avon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lower Farm Solar Photovoltaics · Under Construction | 0.5 | 1.1 km |
Eastfields Farm, Deppers Bridge - Solar Farm Solar Photovoltaics · Under Construction | 34.8 | 1.4 km |
Eastfields Farm, Harbury - Battery Storage Battery · Under Construction | — | 1.4 km |
Ufton Landfill Gas · Operational | 1 | 2.3 km |
Weddington Farm Solar Photovoltaics · Operational | 2.1 | 3 km |
The Elms Solar Photovoltaics · Operational | 10.4 | 4.2 km |
Land On The East Side Of Fosse Way Solar Photovoltaics · Operational | 10 | 4.9 km |
Feldon Vale Solar Farm Solar Photovoltaics · Operational | 49.9 | 5.5 km |
How big is Solar Farm at Fields Farm (Phase 1)?
Solar Farm at Fields Farm (Phase 1) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Solar Farm at Fields Farm (Phase 1)?
REPD records the operator as Foresight Group (TGC Renewables). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Solar Farm at Fields Farm (Phase 1) approved and built?
The application was submitted on 2015-03-16. Permission was granted on 2015-06-29, 3 months later. The site became operational on 2016-03-23, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5244.