Renewable sites › Severn Road
Severn Road
Severn Road is operational in Bristol, City of with a recorded capacity of 4.2 MW, and has been generating since 2023-10-09.
Planning and build timeline
| Application submitted | 2020-03-17 |
| Permission granted | 2021-02-05 11 months after submission |
| Operational | 2023-10-09 32 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Bristol, City of’s record on onshore wind
Bristol, City of has decided 6 onshore wind schemes and approved 100%, taking a median of 4.5 months. See every onshore wind scheme decision in Bristol, City of →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Avonmouth Port II Wind Onshore · Operational | 5 | 0 km |
Severn Road Solar Park Solar Photovoltaics · Operational | 1.8 | 0.7 km |
Avonmouth Resource Recovery Centre (formerly Severn Road) EfW Incineration · Operational | 34 | 1.1 km |
Severnside Energy Recovery Centre EfW Incineration · Operational | 32 | 1.3 km |
Severn Road Battery · Operational | 32 | 2.4 km |
Accolade Wines Wind Onshore · Operational | 2.5 | 2.6 km |
Moorhouse Lane Solar Photovoltaics · Operational | 1.8 | 2.8 km |
Bristol STW (Waste AD) Anaerobic Digestion · Operational | 10 | 2.8 km |
How big is Severn Road?
Severn Road has a recorded installed capacity of 4.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Severn Road?
REPD records the operator as Ambition Community Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Severn Road approved and built?
The application was submitted on 2020-03-17. Permission was granted on 2021-02-05, 11 months later. The site became operational on 2023-10-09, 32 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7524.