Novarly ParcelRenewable sites

Renewable sitesSevern Road

Severn Road

Severn Road is an operational 4.2 MW onshore wind farm in Bristol, City of, generating since 9 October 2023. Planning permission was granted on 5 February 2021, 11 months after submission. Operator of record: Ambition Community Energy.

4.2 MW
Capacity
as recorded in REPD
Operational
Status
since 9 October 2023
Wind Onshore
Technology
Ambition Community Energy
Bristol, City of
Authority
England

Planning and build timeline

Application submitted17 March 2020
Permission granted5 February 2021
11 months after submission
Operational9 October 2023
32 months after consent

Screening a site of your own?

RedlineUK · £39

Bristol, City of approves 100% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Severn Road’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bristol, City of’s record on onshore wind

Bristol, City of has decided 6 onshore wind schemes and approved 100%, taking a median of 4.5 months. See every onshore wind scheme decision in Bristol, City of

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
50 km
Solar Photovoltaics · Operational
1.80.7 km
EfW Incineration · Operational
341.1 km
EfW Incineration · Operational
321.3 km
Battery · Operational
322.4 km
Wind Onshore · Operational
2.52.6 km
Solar Photovoltaics · Operational
1.82.8 km
Anaerobic Digestion · Operational
102.8 km

How big is Severn Road?

Severn Road has a recorded installed capacity of 4.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Severn Road?

REPD records the operator as Ambition Community Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Severn Road approved and built?

The application was submitted on 17 March 2020. Permission was granted on 5 February 2021, 11 months later. The site became operational on 9 October 2023, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7524.