Avonmouth Port II

Avonmouth Port II is operational in Bristol, City of with a recorded capacity of 5 MW, and has been generating since 2013-09-30.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-09-30
Wind Onshore
Technology
Bristol City Council - Energy Management Unit
Bristol, City of
Authority
England

Planning and build timeline

Application submitted2008-08-29
Permission granted2009-01-14
5 months after submission
Operational2013-09-30
57 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bristol, City of’s record on onshore wind

Bristol, City of has decided 6 onshore wind schemes and approved 100%, taking a median of 4.5 months. See every onshore wind scheme decision in Bristol, City of

Other built sites within 15 km

SiteMWDistance
Severn Road
Wind Onshore · Operational
4.20 km
Severn Road Solar Park
Solar Photovoltaics · Operational
1.80.7 km
Avonmouth Resource Recovery Centre (formerly Severn Road)
EfW Incineration · Operational
341.1 km
Severnside Energy Recovery Centre
EfW Incineration · Operational
321.3 km
Severn Road
Battery · Operational
322.4 km
Accolade Wines
Wind Onshore · Operational
2.52.6 km
Land adjacent to Church Road
Solar Photovoltaics · Operational
3.52.8 km
Moorhouse Lane
Solar Photovoltaics · Operational
1.82.8 km

How big is Avonmouth Port II?

Avonmouth Port II has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Avonmouth Port II?

REPD records the operator as Bristol City Council - Energy Management Unit. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Avonmouth Port II approved and built?

The application was submitted on 2008-08-29. Permission was granted on 2009-01-14, 5 months later. The site became operational on 2013-09-30, 57 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3927.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council