Moorhouse Farm, Moorhouse Lane - Solar Park

Moorhouse Farm, Moorhouse Lane - Solar Park is a 3.81 MW solar farm under construction in Bristol, City of. Planning permission was granted on 30 April 2024, 16 months after submission. Operator of record: Cabot Park Solar Limited.

3.81 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Cabot Park Solar Limited
Bristol, City of
Authority
England

Planning and build timeline

Application submitted3 January 2023
Permission granted30 April 2024
16 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Bristol, City of approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Moorhouse Farm, Moorhouse Lane - Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bristol, City of’s record on solar

Bristol, City of has decided 18 solar farms and approved 100%, taking a median of 1.9 months. See every solar farm decision in Bristol, City of

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.80 km
Battery · Operational
320.5 km
Anaerobic Digestion · Operational
100.9 km
Wind Onshore · Operational
8.21.2 km
Solar Photovoltaics · Operational
4.21.6 km
EfW Incineration · Operational
341.7 km
Solar Photovoltaics · Operational
1.82.1 km
Wind Onshore · Operational
2.52.2 km

How big is Moorhouse Farm, Moorhouse Lane - Solar Park?

Moorhouse Farm, Moorhouse Lane - Solar Park has a recorded installed capacity of 3.81 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Moorhouse Farm, Moorhouse Lane - Solar Park?

REPD records the operator as Cabot Park Solar Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Moorhouse Farm, Moorhouse Lane - Solar Park approved and built?

The application was submitted on 3 January 2023. Permission was granted on 30 April 2024, 16 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 13054.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode