Renewable sites › Salcey Solar Farm
Salcey Solar Farm
Salcey Solar Farm is an operational 5 MW solar farm in Milton Keynes, generating since 25 September 2014. Planning permission was granted on 7 March 2014, 3 months after submission. Operator of record: NextEnergy Capital.
Planning and build timeline
| Application submitted | 2 December 2013 |
| Permission granted | 7 March 2014 3 months after submission |
| Operational | 25 September 2014 7 months after consent |
Screening a site of your own?
Milton Keynes approves 91% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Salcey Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Milton Keynes’s record on solar
Milton Keynes has decided 46 solar farms and approved 91%, taking a median of 1.8 months. See every solar farm decision in Milton Keynes →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | 1 | 3.6 km |
Solar Photovoltaics · Operational | 5 | 3.6 km |
Solar Photovoltaics · Operational | 4.7 | 3.8 km |
Solar Photovoltaics · Operational | 14 | 4 km |
Solar Photovoltaics · Operational | 9 | 4.5 km |
Solar Photovoltaics · Operational | 5 | 4.9 km |
Wind Onshore · Operational | 14 | 5 km |
Solar Photovoltaics · Operational | 5 | 5.7 km |
How big is Salcey Solar Farm?
Salcey Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Salcey Solar Farm?
REPD records the operator as NextEnergy Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Salcey Solar Farm approved and built?
The application was submitted on 2 December 2013. Permission was granted on 7 March 2014, 3 months later. The site became operational on 25 September 2014, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1878.