Renewable sitesBulls Head Farm North

Bulls Head Farm North

Bulls Head Farm North is an operational 4.7 MW solar farm in West Northamptonshire, generating since 2 October 2014. Planning permission was granted on 1 April 2014, 4 months after submission. Operator of record: Anesco.

4.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2 October 2014
Solar Photovoltaics
Technology
Anesco
West Northamptonshire
Authority
England

Planning and build timeline

Application submitted12 December 2013
Permission granted1 April 2014
4 months after submission
Operational2 October 2014
6 months after consent

Screening a site of your own?

RedlineUK · £39

West Northamptonshire approves 92% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bulls Head Farm North’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Northamptonshire’s record on solar

West Northamptonshire has decided 61 solar farms and approved 92%, taking a median of 2.9 months. See every solar farm decision in West Northamptonshire

Other built sites within 15 km

SiteMWDistance
Battery · Operational
10.7 km
Solar Photovoltaics · Operational
143.1 km
Solar Photovoltaics · Operational
53.1 km
Solar Photovoltaics · Operational
53.4 km
Wind Onshore · Operational
7.23.6 km
Solar Photovoltaics · Operational
53.8 km
Anaerobic Digestion · Under Construction
4.6 km
Solar Photovoltaics · Operational
4.95.8 km

How big is Bulls Head Farm North?

Bulls Head Farm North has a recorded installed capacity of 4.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bulls Head Farm North?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bulls Head Farm North approved and built?

The application was submitted on 12 December 2013. Permission was granted on 1 April 2014, 4 months later. The site became operational on 2 October 2014, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1976.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode