Renewable sites › Hyde Farm
Hyde Farm
Hyde Farm is operational in Milton Keynes with a recorded capacity of 5 MW, and has been generating since 2017-03-16.
Planning and build timeline
| Application submitted | 2015-08-07 |
| Permission granted | 2016-01-12 5 months after submission |
| Operational | 2017-03-16 14 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Milton Keynes’s record on solar
Milton Keynes has decided 46 solar farms and approved 91%, taking a median of 1.8 months. See every solar farm decision in Milton Keynes →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rectory Farm/Emberton Solar Photovoltaics · Operational | 9 | 4.5 km |
Salcey Solar Farm Solar Photovoltaics · Operational | 5 | 4.9 km |
Milton Keynes Wind Farm Wind Onshore · Operational | 14 | 5 km |
Manor Farm (Horton) Solar Photovoltaics · Operational | 5 | 5.3 km |
Land East of Horton Road Solar Photovoltaics · Operational | 4.9 | 7.1 km |
Bulls Head Farm North Solar Photovoltaics · Operational | 4.7 | 7.8 km |
Salcey Solar Farm Battery · Operational | 1 | 7.9 km |
Littlewood Farm Solar Photovoltaics · Operational | 14 | 8.9 km |
How big is Hyde Farm?
Hyde Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hyde Farm?
REPD records the operator as Conergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hyde Farm approved and built?
The application was submitted on 2015-08-07. Permission was granted on 2016-01-12, 5 months later. The site became operational on 2017-03-16, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5685.