Novarly ParcelRenewable sites

Renewable sitesHyde Farm

Hyde Farm

Hyde Farm is operational in Milton Keynes with a recorded capacity of 5 MW, and has been generating since 2017-03-16.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-16
Solar Photovoltaics
Technology
Conergy
Milton Keynes
Authority
England

Planning and build timeline

Application submitted2015-08-07
Permission granted2016-01-12
5 months after submission
Operational2017-03-16
14 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Milton Keynes’s record on solar

Milton Keynes has decided 46 solar farms and approved 91%, taking a median of 1.8 months. See every solar farm decision in Milton Keynes

Other built sites within 15 km

SiteMWDistance
Rectory Farm/Emberton
Solar Photovoltaics · Operational
94.5 km
Salcey Solar Farm
Solar Photovoltaics · Operational
54.9 km
Milton Keynes Wind Farm
Wind Onshore · Operational
145 km
Manor Farm (Horton)
Solar Photovoltaics · Operational
55.3 km
Land East of Horton Road
Solar Photovoltaics · Operational
4.97.1 km
Bulls Head Farm North
Solar Photovoltaics · Operational
4.77.8 km
Salcey Solar Farm
Battery · Operational
17.9 km
Littlewood Farm
Solar Photovoltaics · Operational
148.9 km

How big is Hyde Farm?

Hyde Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hyde Farm?

REPD records the operator as Conergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hyde Farm approved and built?

The application was submitted on 2015-08-07. Permission was granted on 2016-01-12, 5 months later. The site became operational on 2017-03-16, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5685.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council