Novarly ParcelRenewable sites

Renewable sitesMilton Keynes Wind Farm

Milton Keynes Wind Farm

Milton Keynes Wind Farm is an operational 14 MW onshore wind farm in Milton Keynes, generating since 25 September 2010. Planning permission was granted on 14 January 2008, 17 months after submission. Operator of record: Gravis Capital Management.

14 MW
Capacity
as recorded in REPD
Operational
Status
since 25 September 2010
Wind Onshore
Technology
Gravis Capital Management
Milton Keynes
Authority
England

Planning and build timeline

Application submitted18 August 2006
Permission granted14 January 2008
17 months after submission
Operational25 September 2010
32 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Milton Keynes: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Milton Keynes Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
90.6 km
Solar Photovoltaics · Operational
55 km
Solar Photovoltaics · Operational
55 km
Solar Photovoltaics · Operational
55.6 km
Solar Photovoltaics · Under Construction
0.267 km
Solar Photovoltaics · Operational
58 km
Solar Photovoltaics · Operational
0.448 km
Solar Photovoltaics · Operational
0.888 km

How big is Milton Keynes Wind Farm?

Milton Keynes Wind Farm has a recorded installed capacity of 14 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Milton Keynes Wind Farm?

REPD records the operator as Gravis Capital Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Milton Keynes Wind Farm approved and built?

The application was submitted on 18 August 2006. Permission was granted on 14 January 2008, 17 months later. The site became operational on 25 September 2010, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2968.