Rectory Farm/Emberton
Rectory Farm/Emberton is operational in Milton Keynes with a recorded capacity of 9 MW, and has been generating since 2015-03-31.
Planning and build timeline
| Application submitted | 2014-02-26 |
| Permission granted | 2014-09-12 7 months after submission |
| Operational | 2015-03-31 7 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Milton Keynes’s record on solar
Milton Keynes has decided 46 solar farms and approved 91%, taking a median of 1.8 months. See every solar farm decision in Milton Keynes →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Milton Keynes Wind Farm Wind Onshore · Operational | 14 | 0.6 km |
Hyde Farm Solar Photovoltaics · Operational | 5 | 4.5 km |
Salcey Solar Farm Solar Photovoltaics · Operational | 5 | 4.5 km |
The Kickles Solar Photovoltaics · Operational | 5 | 5.7 km |
Caldecote Farm - Storage & Distribution Unit Solar Photovoltaics · Under Construction | 0.26 | 7.3 km |
Manor Farm (Horton) Solar Photovoltaics · Operational | 5 | 7.4 km |
Littlewood Farm Solar Photovoltaics · Operational | 14 | 7.8 km |
Salcey Solar Farm Battery · Operational | 1 | 8 km |
How big is Rectory Farm/Emberton?
Rectory Farm/Emberton has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rectory Farm/Emberton?
REPD records the operator as Low Carbon. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rectory Farm/Emberton approved and built?
The application was submitted on 2014-02-26. Permission was granted on 2014-09-12, 7 months later. The site became operational on 2015-03-31, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2144.