Safran Landing Systems Service is operational in Tewkesbury with a recorded capacity of 3.6 MW, and has been generating since 2017-03-29.
Planning and build timeline
| Application submitted | 2016-12-09 |
| Permission granted | 2022-08-03 68 months after submission |
| Operational | 2017-03-29 |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Meteor Business Park Battery · Operational | 1.5 | 0.1 km |
Plant 1, G-Tekt Europe Manufacturing Limited -Roof Mounted Solar Panels Solar Photovoltaics · Under Construction | 1 | 5.8 km |
Home Farm Solar Photovoltaics · Operational | 6.7 | 7 km |
Troughton Farm Solar Photovoltaics · Operational | 30 | 7.7 km |
Wingmoor Farm (Waste AD) Anaerobic Digestion · Operational | 1.6 | 8.1 km |
Mobile Telephone Exchange (MTX) - Solar Panels Solar Photovoltaics · Operational | — | 10.3 km |
Moog Controls Factory Solar Photovoltaics · Operational | 0.38 | 12 km |
Highleadon - Solar Arrays & Battery Storage Battery · Operational | — | 12 km |
How big is Safran Landing Systems Service?
Safran Landing Systems Service has a recorded installed capacity of 3.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Safran Landing Systems Service?
REPD records the operator as Safran Landing Systems UK/Technical Plant Services. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Safran Landing Systems Service approved and built?
The application was submitted on 2016-12-09. Permission was granted on 2022-08-03, 68 months later. The site became operational on 2017-03-29.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6367.