Ruabon is an operational 2.1 MW landfill gas site in Wrexham, generating since 15 July 2001. Planning permission was granted on 5 December 2000, 12 months after submission. Operator of record: Waste Recycling Group.

2.1 MW
Capacity
as recorded in REPD
Operational
Status
since 15 July 2001
Landfill Gas
Technology
Waste Recycling Group
Wrexham
Authority
Wales

Planning and build timeline

Application submitted29 November 1999
Permission granted5 December 2000
12 months after submission
Operational15 July 2001
7 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Wrexham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ruabon’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
51.4 km
Solar Photovoltaics · Operational
52.1 km
Landfill Gas · Operational
2.33.5 km
Solar Photovoltaics · Operational
33.9 km
Solar Photovoltaics · Operational
5.46 km
Solar Photovoltaics · Operational
17.4 km
Solar Photovoltaics · Operational
0.418.3 km
Solar Photovoltaics · Operational
3.68.5 km

How big is Ruabon?

Ruabon has a recorded installed capacity of 2.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ruabon?

REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ruabon approved and built?

The application was submitted on 29 November 1999. Permission was granted on 5 December 2000, 12 months later. The site became operational on 15 July 2001, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 544.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode