Ruabon is operational in Wrexham with a recorded capacity of 2.1 MW, and has been generating since 2001-07-15.

2.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2001-07-15
Landfill Gas
Technology
Waste Recycling Group
Wrexham
Authority
Wales

Planning and build timeline

Application submitted1999-11-29
Permission granted2000-12-05
12 months after submission
Operational2001-07-15
7 months after consent

Other built sites within 15 km

SiteMWDistance
Penycae Solar Farm
Solar Photovoltaics · Operational
51.4 km
Land Opposite Tyn Y Pistyll
Solar Photovoltaics · Operational
52.1 km
Pen y Bont
Landfill Gas · Operational
2.33.5 km
Bronwylfa Reservoir
Solar Photovoltaics · Operational
33.9 km
Wrexham Social Housing PV
Solar Photovoltaics · Operational
5.46 km
Knolton Farmhouse Cheese Solar Farm
Solar Photovoltaics · Operational
17.4 km
F Lloyd Penley - Solar Panels
Solar Photovoltaics · Operational
0.418.3 km
Land NW Of Pickhill Bridge Farm
Solar Photovoltaics · Operational
3.68.5 km

How big is Ruabon?

Ruabon has a recorded installed capacity of 2.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ruabon?

REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ruabon approved and built?

The application was submitted on 1999-11-29. Permission was granted on 2000-12-05, 12 months later. The site became operational on 2001-07-15, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 544.