Novarly ParcelRenewable sites

Renewable sitesLand Opposite Tyn Y Pistyll

Land Opposite Tyn Y Pistyll

Land Opposite Tyn Y Pistyll is an operational 5 MW solar farm in Wrexham, generating since 22 December 2015. Planning permission was granted on 12 May 2015, 3 months after submission. Operator of record: Lightsource Renewable Energy.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 22 December 2015
Solar Photovoltaics
Technology
Lightsource Renewable Energy
Wrexham
Authority
Wales

Planning and build timeline

Application submitted10 February 2015
Permission granted12 May 2015
3 months after submission
Operational22 December 2015
7 months after consent

Screening a site of your own?

RedlineUK · £39

Wrexham approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land Opposite Tyn Y Pistyll’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Wrexham’s record on solar

Wrexham has decided 15 solar farms and approved 100%, taking a median of 5 months. See every solar farm decision in Wrexham

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.7 km
Landfill Gas · Operational
2.12.1 km
Landfill Gas · Operational
2.32.5 km
Solar Photovoltaics · Operational
35 km
Solar Photovoltaics · Operational
5.48 km
Solar Photovoltaics · Operational
18.3 km
Solar Photovoltaics · Operational
0.4110.4 km
Solar Photovoltaics · Operational
510.4 km

How big is Land Opposite Tyn Y Pistyll?

Land Opposite Tyn Y Pistyll has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land Opposite Tyn Y Pistyll?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land Opposite Tyn Y Pistyll approved and built?

The application was submitted on 10 February 2015. Permission was granted on 12 May 2015, 3 months later. The site became operational on 22 December 2015, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5026.