Renewable sites › Land Opposite Tyn Y Pistyll
Land Opposite Tyn Y Pistyll
Land Opposite Tyn Y Pistyll is an operational 5 MW solar farm in Wrexham, generating since 22 December 2015. Planning permission was granted on 12 May 2015, 3 months after submission. Operator of record: Lightsource Renewable Energy.
Planning and build timeline
| Application submitted | 10 February 2015 |
| Permission granted | 12 May 2015 3 months after submission |
| Operational | 22 December 2015 7 months after consent |
Screening a site of your own?
Wrexham approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land Opposite Tyn Y Pistyll’s recorded coordinate — swap in your own postcode or coordinates.
Wrexham’s record on solar
Wrexham has decided 15 solar farms and approved 100%, taking a median of 5 months. See every solar farm decision in Wrexham →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 0.7 km |
Landfill Gas · Operational | 2.1 | 2.1 km |
Landfill Gas · Operational | 2.3 | 2.5 km |
Solar Photovoltaics · Operational | 3 | 5 km |
Solar Photovoltaics · Operational | 5.4 | 8 km |
Solar Photovoltaics · Operational | 1 | 8.3 km |
Solar Photovoltaics · Operational | 0.41 | 10.4 km |
Solar Photovoltaics · Operational | 5 | 10.4 km |
How big is Land Opposite Tyn Y Pistyll?
Land Opposite Tyn Y Pistyll has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land Opposite Tyn Y Pistyll?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land Opposite Tyn Y Pistyll approved and built?
The application was submitted on 10 February 2015. Permission was granted on 12 May 2015, 3 months later. The site became operational on 22 December 2015, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5026.