Renewable sitesPen y Bont

Pen y Bont

Pen y Bont is an operational 2.3 MW landfill gas site in Wrexham, generating since 2 January 2003. Planning permission was granted on 8 July 2002, 4 months after submission. Operator of record: Waste Recycling Group.

2.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2 January 2003
Landfill Gas
Technology
Waste Recycling Group
Wrexham
Authority
Wales

Planning and build timeline

Application submitted12 March 2002
Permission granted8 July 2002
4 months after submission
Operational2 January 2003
6 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Wrexham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pen y Bont’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
52.4 km
Solar Photovoltaics · Operational
52.5 km
Landfill Gas · Operational
2.13.5 km
Solar Photovoltaics · Operational
16.8 km
Solar Photovoltaics · Operational
37.2 km
Solar Photovoltaics · Operational
57.9 km
Solar Photovoltaics · Operational
5.49.3 km
Solar Photovoltaics · Operational
7.29.6 km

How big is Pen y Bont?

Pen y Bont has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pen y Bont?

REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pen y Bont approved and built?

The application was submitted on 12 March 2002. Permission was granted on 8 July 2002, 4 months later. The site became operational on 2 January 2003, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 543.