Renewable sites › Land NW Of Pickhill Bridge Farm
Land NW Of Pickhill Bridge Farm
Land NW Of Pickhill Bridge Farm is operational in Wrexham with a recorded capacity of 3.6 MW, and has been generating since 2017-03-24.
Planning and build timeline
| Application submitted | 2015-04-13 |
| Permission granted | 2015-07-31 4 months after submission |
| Operational | 2017-03-24 20 months after consent |
Wrexham’s record on solar
Wrexham has decided 15 solar farms and approved 100%, taking a median of 5 months. See every solar farm decision in Wrexham →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Williams Farm Solar Photovoltaics · Operational | 5 | 0.6 km |
F Lloyd Penley - Solar Panels Solar Photovoltaics · Operational | 0.41 | 1.2 km |
Wrexham Social Housing PV Solar Photovoltaics · Operational | 5.4 | 4.7 km |
Knolton Farmhouse Cheese Solar Farm Solar Photovoltaics · Operational | 1 | 7.6 km |
Ruabon Landfill Gas · Operational | 2.1 | 8.5 km |
Trench Farm Solar Photovoltaics · Operational | 7.2 | 8.8 km |
Bronwylfa Reservoir Solar Photovoltaics · Operational | 3 | 9 km |
Penycae Solar Farm Solar Photovoltaics · Operational | 5 | 9.8 km |
How big is Land NW Of Pickhill Bridge Farm?
Land NW Of Pickhill Bridge Farm has a recorded installed capacity of 3.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land NW Of Pickhill Bridge Farm?
REPD records the operator as NextEnergy Solar Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land NW Of Pickhill Bridge Farm approved and built?
The application was submitted on 2015-04-13. Permission was granted on 2015-07-31, 4 months later. The site became operational on 2017-03-24, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5226.
Novarly Parcel · official public data, read properly · parcel.novarly.com