Novarly ParcelRenewable sites

Renewable sitesRothes Bio-Plant

Rothes Bio-Plant

Rothes Bio-Plant is operational in Moray with a recorded capacity of 8.3 MW, and has been generating since 2013-04-16.

8.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-04-16
Biomass (dedicated)
Technology
Scottish Bio-Power
Moray
Authority
Scotland

Planning and build timeline

Application submitted2008-03-17
Permission granted2009-01-28
10 months after submission
Operational2013-04-16
51 months after consent

Other built sites within 15 km

SiteMWDistance
Speyside Biomass CHP Plant
Biomass (dedicated) · Operational
12.53.5 km
Rothes Wind (Cairn Uish)
Wind Onshore · Operational
50.69.4 km
Rothes Wind Farm (Extension) (II)
Wind Onshore · Operational
41.49.4 km
Glenfiddich Distillery
Anaerobic Digestion · Operational
1.59.5 km
Garbet Windfarm - Wind Farm & Storage facility
Battery · Under Construction
310.1 km
Garbet Windfarm - Wind Farm & Storage facility
Wind Onshore · Under Construction
46.210.1 km
Hill of Towie (Drummuir)
Wind Onshore · Operational
4813.4 km
Edintore Wind Farm
Wind Onshore · Operational
1814.9 km

How big is Rothes Bio-Plant?

Rothes Bio-Plant has a recorded installed capacity of 8.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Rothes Bio-Plant?

REPD records the operator as Scottish Bio-Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Rothes Bio-Plant approved and built?

The application was submitted on 2008-03-17. Permission was granted on 2009-01-28, 10 months later. The site became operational on 2013-04-16, 51 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 140.

Novarly Parcel · official public data, read properly · parcel.novarly.com