Edintore Wind Farm is an operational 18 MW onshore wind farm in Moray, generating since 31 October 2016. Planning permission was granted on 28 August 2012, 21 months after submission. Operator of record: Vento Ludens.

18 MW
Capacity
as recorded in REPD
Operational
Status
since 31 October 2016
Wind Onshore
Technology
Vento Ludens
Moray
Authority
Scotland

Planning and build timeline

Application submitted11 December 2010
Permission granted28 August 2012
21 months after submission
Operational31 October 2016
50 months after consent

Screening a site of your own?

RedlineUK · £39

Moray approves 77% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Edintore Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Moray’s record on onshore wind

Moray has decided 13 onshore wind schemes and approved 77%, taking a median of 16.4 months. See every onshore wind scheme decision in Moray

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
3001.7 km
Wind Onshore · Operational
106 km
Anaerobic Digestion · Operational
1.511.2 km
Wind Onshore · Under Construction
46.212 km
Battery · Under Construction
312 km
Wind Onshore · Operational
4.612.6 km
Wind Onshore · Operational
1.612.6 km
Biomass (dedicated) · Operational
12.514.8 km

How big is Edintore Wind Farm?

Edintore Wind Farm has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Edintore Wind Farm?

REPD records the operator as Vento Ludens. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Edintore Wind Farm approved and built?

The application was submitted on 11 December 2010. Permission was granted on 28 August 2012, 21 months later. The site became operational on 31 October 2016, 50 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4072.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode